You need to set a baseline for the project
You are a project manager for an organization that uses Project Server 2013.
Only administrators have Project Professional 2013. You use Project Web App (PWA) for schedule
management.
You modify your schedule after some changes are approved through your organization’s Project
Scope Change process.
You need to set a baseline for the project.
What should you do?
you need to reserve proposed demand for the final 12 months
You are a project manager who uses Project Online. Your project is scheduled to run for at least 18
months. You create a schedule for the first six months, including estimated resource demand, using
Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?
You need to create a tasks-assignment process that meets the following requirements:
You are a new project manager in the software development department. Your company uses
Project Server 2013. The software development department has 100 developers that are members
of a team named Developers. A generic resource named developer is also a member of this team.
Only the generic resource has checked the Team Assignment Pool option in the Team Details section
in the Resource page definition.
You plan to create a new project, but you do not know which developers have the availability and
proper skills to perform the tasks.
You need to create a tasks-assignment process that meets the following requirements:
• Let the developers choose which tasks they want to participate in based on their
availabilities and skills.
• Review and approve the resources assignments.
• Use the least amount of time possible.
What should you do?
You need to reconfigure Project Server 2013 to enable the skills match function
You are the administrator of a Project Server 2013 environment.
You set up an enterprise custom resource field to define skill sets for resources. When trying to
replace your generic resources, the matching function does not work.
You need to reconfigure Project Server 2013 to enable the skills match function.
What should you do?
You need to solve this problem
You are a project manager, and your organization uses Project Server 2013 with an enterprise
resource pool.
After assigning resources, you discover that two of them are showing up as overallocated. These two
resources also work on other projects that you cannot change.
You need to solve this problem.
What should you do?
You need to remove the resource demand from the resource plan
You are a project manager for an organization that uses Project Online.
You create a resource plan to provide high level resource demand during the portfolio intake and
selection process.
Your project is now selected for detailed planning. You complete a detailed work breakdown
structure (WBS).
You need to remove the resource demand from the resource plan.
What should you do?
You need to see the correct demand
You are a project manager who uses Project Online.
You build and publish a resource plan for your project. You check the resource demand in the
Resource Availability screen.
You do not see the correct demand as defined in the resource plan.
You need to see the correct demand.
What should you do?
You need to configure your resources to enable this method of assigning tasks
You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a
project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them
assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?
You need to determine if a team member has available capacity to assist on another project or if this team mem
You are a project manager for an organization that uses Project Server 2013.
You are evaluating resource information in the Resource Center. The following information is
presented to you on the Resource Availability page:
You need to determine if a team member has available capacity to assist on another project or if this
team member is overallocated.
What should you do?
You need to allow project managers to plan workload and cost from the task level up
You are a Project Server 2013 administrator, and you support the Project Management Office (PMO)
project managers who need to estimate project hours and costs without knowing the specific
resource names.
There are options available to accommodate this request when creating resources on Project Server
2013.
You need to allow project managers to plan workload and cost from the task level up.
What should you do?