You need to create a tasks-assignment process that meets the following requirements:

You are a new project manager in the software development department. Your company uses
Project Server 2013. The software development department has 100 developers that are members
of a team named Developers. A generic resource named developer is also a member of this team.
Only the generic resource has checked the Team Assignment Pool option in the Team Details section
in the Resource page definition.
You plan to create a new project, but you do not know which developers have the availability and
proper skills to perform the tasks.
You need to create a tasks-assignment process that meets the following requirements:
• Let the developers choose which tasks they want to participate in based on their
availabilities and skills.
• Review and approve the resources assignments.
• Use the least amount of time possible.
What should you do?

You need to remove the resource demand from the resource plan

You are a project manager for an organization that uses Project Online.
You create a resource plan to provide high level resource demand during the portfolio intake and
selection process.

Your project is now selected for detailed planning. You complete a detailed work breakdown
structure (WBS).
You need to remove the resource demand from the resource plan.
What should you do?

You need to configure your resources to enable this method of assigning tasks

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a
project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them
assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?

You need to determine if a team member has available capacity to assist on another project or if this team mem

You are a project manager for an organization that uses Project Server 2013.
You are evaluating resource information in the Resource Center. The following information is
presented to you on the Resource Availability page:

You need to determine if a team member has available capacity to assist on another project or if this
team member is overallocated.
What should you do?

You need to allow project managers to plan workload and cost from the task level up

You are a Project Server 2013 administrator, and you support the Project Management Office (PMO)
project managers who need to estimate project hours and costs without knowing the specific
resource names.
There are options available to accommodate this request when creating resources on Project Server
2013.
You need to allow project managers to plan workload and cost from the task level up.
What should you do?