PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

You need to optimize the statement

You are developing a database application by using Microsoft SQL Server 2012.
An application that uses a database begins to run slowly.
You discover that the root cause is a query against a frequently updated table that has a clustered
index. The query returns four columns: three columns in its WHERE clause contained in a nonclustered index and one additional column.
You need to optimize the statement.
What should you do?

which column in the Employee table should you create a Foreign Key constraint that references a different tabl

You administer a Microsoft SQL Server 2012 database.
The database contains a table named Employee. Part of the Employee table is shown in the exhibit.
(Click the Exhibit button.)

Unless stated above, no columns in the Employee table reference other tables.
Confidential information about the employees is stored in a separate table named EmployeeData.
One record exists within EmployeeData for each record in the Employee table.
You need to assign the appropriate constraints and table properties to ensure data integrity and
visibility.
On which column in the Employee table should you create a Foreign Key constraint that references a
different table in the database?

which column in the Employee table should you create a Primary Key constraint for this table?

You administer a Microsoft SQL Server 2012 database.

The database contains a table named Employee. Part of the Employee table is shown in the exhibit.
(Click the Exhibit button.)

Unless stated above, no columns in the Employee table reference other tables.
Confidential information about the employees is stored in a separate table named EmployeeData.
One record exists within EmployeeData for each record in the Employee table.
You need to assign the appropriate constraints and table properties to ensure data integrity and
visibility.
On which column in the Employee table should you create a Primary Key constraint for this table?

A project manager calls you to report they are unable to open your project for edit in PW

You are a project manager in an organization that uses Project Server 2013. All project managers
have permission to edit all projects.
You edit a project in Project Web App (PWA), make changes, publish the project, and close your
browser.
A project manager calls you to report they are unable to open your project for edit in PWA.
You need to resolve this issue. What should you do?

Which element should you use?

Your organization is performing a Portfolio Analysis in Project Server 2013.
You want to create a consolidated Portfolio Analysis optimization based on Cost and Resource data,
which will be part of the project information in Project Server 2013.
You plan to provide different simulations to your organization by using those parameters and
returning the best prioritization.
This organization has two different unit directors, who have the final decision on the consolidated
Portfolio Analysis results.
You need to provide the ability for your unit directors to modify the final portfolio selection.
Which element should you use?

You need to generate a solution that allows R&D to gather their ideas and facilitate the materialization i

Your organization is a multinational corporation that uses Project Online to plan and control the
projects in different business units. Each business unit has its own portfolio of projects but can
participate in strategic projects.
The Research and Development (R&D) department has been struggling to gather and materialize the
new ideas. The Project Management Office (PMO) has the necessary templates and Enterprise
Project Types (EPTs) to start a formal process for any new product and to adhere to the general
guidelines. However, the R&D group does not want to register all of their ideas since many are
related to improvements and few of them could be materialized into projects.
You need to generate a solution that allows R&D to gather their ideas and facilitate the
materialization into Enterprise Projects.
What should you do?

You need to guarantee that the analysis will produce the most viable proposal in terms of cost and resources a

Your organization uses Project Online for project portfolio selection. The business drivers and
priorities are set, as are the main constraints to identify the efficient frontier.
The company has been collecting business cases for new proposals in which many projects may solve
the same business need. For example, the selection for a Customer Relationship Management
system has six different proposals, whereas only one is necessary to fulfill the business need.
You need to guarantee that the analysis will produce the most viable proposal in terms of cost and
resources and that no repetitive efforts exist in the portfolio selection.
What should you do?

You need to maintain ownership and authority of key program dates at the program level

You are a program manager for an organization that uses Project Server 2013.
You are responsible for implementing a data warehouse that compiles relational data from many
business areas. Your project managers need to be able to manage the implementation for a business
area as separate projects, while still recognizing the dependencies at a program level.
You need to maintain ownership and authority of key program dates at the program level.
What should you do?

What are two possible ways to achieve this goal?

You are a program manager for a company that uses Project Server 2013 and Project Professional
2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)