A security camera is connected to an EX Series switch. You are asked to ensure power to
the PoE port is maintained if the power budget is exceeded. Which two actions will
accomplish this task? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Set the PoE management mode to static.

B.
Set the PoE management mode to class.

C.
Set the PoE interface priority to high.

D.
Ensure the camera is connected to port ge-0/0/0.