Which of the following statements describing how identified product quality risks should be
mitigated and managed, is true?
A.
The extent of re-testing and regression testing activities should be based on the risk level
B.
The identification of new risks, the re-assessment of the level of existing risks and the
evaluation of the effectiveness of risk mitigation activities should only occur at the very beginning
of a project
C.
Risk mitigation of product quality risks can be effective only after starting test execution
D.
The priority of the development and execution of tests should not be based on the risk level but
only on the likelihood
Explanation: