Which of the following activities should be carried out at the start of this process?

Topic 4, Case Study# 4 Scenario
A bank is upgrading its systems to include an on-line investment service, allowing investors to
trade with each other, in a mini-stock market environment.
The upgrade will be carried out using Agile development (within the Scrum framework). Here, the
iterations are referred to as Sprints. For each Sprint the required functionality will be defined as a
set of user-stories. The user stories are typically 1-2 lines long, indicating what the business wants
the system to do. These user stories will be built then tested.
There will be 3 Sprints:
1) Creation of the mini-stock market trading environment.
2) Creation of additional front-end enhancements.
3) Linking to stock exchange for pricing.
You are the test manager. You lead a team of 4 testers, and there are 6 developers. Your team
has worked on Agile projects previously, and on average, Sprints usually last 4 weeks. At the end
of all Sprints, a full end to end test is carried out. This is called the E2E test phase. You are
worried that 4 weeks will not be sufficient time for the first Sprint. You have decided to conduct a
Risk Management exercise before the project starts.
*************************************

Which of the following activities should be carried out at the start of this process?

PrepAway - Latest Free Exam Questions & Answers

A.
Marketing of the service to as many people as possible to reduce the risk of poor revenues.

B.
Holding a workshop with as many stakeholders as possible to gain their views on the risks to
the product and project.

C.
Meeting with the project manager to agree a bigger budget.

D.
Meeting with the development manager to agree defect fix turn-around times.

Explanation: