What should he/she do?

The development manager has reviewed the initial inspection results in the company and has
discovered that your inspection logging rate is 2 issues per minute and the average checking rate
is 5 pages per hour. Around 10 major defects are found per page. The manager is willing to
invest more money in your inspection programme. What should he/she do?

PrepAway - Latest Free Exam Questions & Answers

A.
Ask checkers to try a checking rate of 6 pages per hour

B.
Make sure the scribe logs issues at a rate of 1 issue per minute

C.
Ask moderators to cut back on discussion in the logging meeting

D.
Ask checkers to try a checking rate of 4 pages per hour

Explanation: