What things will you need as inputs for the quantitative risk analysis of the project in this scenario?

You are the project manager of the GGH Project in your company. Your company is
structured as a functional organization and you report to the functional manager that you are
ready to move onto the quantitative risk analysis process. What things will you need as
inputs for the quantitative risk analysis of the project in this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
You will need the risk register, risk management plan, permission from the
functional manager, and any relevant organizational process assets.

B.
You will need the risk register, risk management plan, outputs of qualitative risk
analysis, and any relevant organizational process assets.

C.
You will need the risk register, risk management plan, cost management plan,
schedule management plan, and any relevant organizational process assets.

D.
Quantitative risk analysis does not happen through the project manager in a
functional stru cture.