For your project archives, which one of the following is an output of risk monitoring and control

You are working as a project manager in your organization. You are nearing the final stages of
project execution and looking towards the final risk monitoring and controlling activities. For your
project archives, which one of the following is an output of risk monitoring and control

PrepAway - Latest Free Exam Questions & Answers

A.
Quantitative risk analysis

B.
Risk audits

C.
Requested changes

D.
Qualitative risk analysis