What happens when the project manager crashes a project?

Your organization has named you the project manager of the JKN Project. This project has
a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if
the schedule baseline has a variance of more than five percent then you will need to crash
the project. What happens when the project manager crashes a project?

PrepAway - Latest Free Exam Questions & Answers

A.
The amount of hours a resource can be used will diminish.

B.
The projectwill take longer to complete, but risks will diminish.

C.
Project risks will increase.

D.
Project costs will increase.