ISACA Exam Questions

Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk
analysis process for your project. You can use three available tools and techniques to complete
this process. Which one of the following is NOT a tool or technique that is appropriate for the
quantitative risk analysis process?

A.
Quantitative risk analysis and modeling techniques

B.
Organizational process assets

C.
Expert judgment

D.
Data gathering and representation techniques

Explanation: