When will the quantitative risk analysis process need to be repeated?

Fred is the project manager of the PKL project. He is working with his project team to complete the
quantitative risk analysis process as a part of risk management planning.
Fred understands that once the quantitative risk analysis process is complete, the process will
need to be completed again in at least two other times in the project. When will the quantitative
risk analysis process need to be repeated?