Once an organization has finished the business process reengineering (BPR) of all its critical operations, an IS auditor would MOST likely focus on a review of:

A.
pre-BPR process flowcharts.
B.
post-BPR process flowcharts.
C.
BPR project plans.
D.
continuous improvement and monitoring plans.
Explanation:
An IS auditor’s task is to identify and ensure that key controls have been incorporated into the reengineered process. Choice A is incorrect because an IS auditor must review the process as it is today, not as it was in the past. Choices C and D areincorrect because they are steps within a BPR project.
I have the same idea. B