The PRIMARY focus of the change control process is to ensure that changes are:

A. authorized.

B. applied.

C. documented.

D. tested.

Explanation: All steps in the change control process must be signed off on to ensure proper authorization. It is important that changes are applied, documented and tested; however, they are not the primary focus.