Risk acceptance is a component of which of the following?
A. Assessment
B. Mitigation
C. Evaluation
D. Monitoring
Explanation:
Risk acceptance is one of the alternatives to be considered in the risk mitigation process. Assessment and evaluation are components of the risk analysis process. Risk acceptance is not a component of monitoring.