Which of the following domains of CGEIT aims to guarantee that the IT enables and supports the achievement of
Which of the following domains of CGEIT aims to guarantee that the IT enables and supports the
achievement of business objectives through the integration of IT strategic plans with business
strategic plans and the alignment of IT services with enterprise operations?
How many communication channels exist in this project?
You are the project manager for the ABC organization. Your current project has 75 internal
stakeholders and 245 external stakeholders. Many of the risks within your project will only affect
the internal stakeholders, but several of the identified risk events will affect the external
stakeholders. Management would like to know the total number of communication channels in the
project. How many communication channels exist in this project?
Which of the following is a process improvement approach that provides organizations with the essential elemen
Which of the following is a process improvement approach that provides organizations with the
essential elements for effective process improvement and guides process improvement across a
project, a division, or an entire organization?
What approach can Amy take to create a bias against risks that will affect the schedule of the project?
Amy is the project manager for her company. In her current project the organization has a very low
tolerance for risk events that will affect the project schedule. Management has asked Amy to
consider the affect of all the risks on the project schedule. What approach can Amy take to create
a bias against risks that will affect the schedule of the project?
Which of the following inputs will be needed for the quantitative risk analysis process in her project?
Della works as a project manager for SoftTech Inc. She is working with the project stakeholders to
begin the quantitative risk analysis process. Which of the following inputs will be needed for the
quantitative risk analysis process in her project? Each correct answer represents a complete
solution. Choose all that apply.
Which types of project tends to have more well-understood risks?
Which types of project tends to have more well-understood risks?
What type of risk response is this approach?
Marsha is the project manager of the NHQ Project. There’s a risk that her project team has
identified, which could cause the project to be late by more than a month. Marsha does not want
this risk event to happen so she devises extra project activities to ensure that the risk event will not
happen. The extra steps, however, will cost the project an additional $10,000. What type of risk
response is this approach?
Which of the following frameworks describes a standard for processes within business information management at
Which of the following frameworks describes a standard for processes within business information
management at the strategy, management and operations level?
which of the following processes are you on?
You are the project manager of a large construction project. You are evaluating the strengths,
weaknesses, opportunities, and threats involved in a project. In which of the following processes
are you on?
Which of the following is NOT a valid maturity level of the Software Capability Maturity Model (CMM)?
Which of the following is NOT a valid maturity level of the Software Capability Maturity Model
(CMM)?