PrepAway - Latest Free Exam Questions & Answers

Category: CGEIT

Exam CGEIT: ISACA CGEIT Certification

Which of the following elements of Availability Management is used to perform at an agreed level over a period

Availability Management allows organizations to sustain the IT service availability to support the
business at a justifiable cost. Which of the following elements of Availability Management is used
to perform at an agreed level over a period of time?
Each correct answer represents a part of the solution. Choose all that apply.

Which one of the following is a valid response to the identified risk event?

Your project team has identified a project risk that must be responded to. The risk has been
recorded in the risk register and the project team has been discussing potential risk responses for
the risk event. The event is not likely to happen for several months but the probability of the event
is high. Which one of the following is a valid response to the identified risk event?