What risk identification method could you use?

Your project spans the entire organization. You would like to assess the risk of your project but
worried about that some of the managers involved in the project could affect the outcome of any
risk identification meeting. Your consideration is based on the fact that some employees would not
want to publicly identify risk events that could declare their supervision as poor. You would like a
method that would allow participants to anonymously identify risk events. What risk identification
method could you use?

Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis p

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk
analysis process for your project. You can use three available tools and techniques to complete
this process. Which one of the following is NOT a tool or technique that is appropriate for the
quantitative risk analysis process?

what term?

You work as a project manager for BlueWell Inc. Your project is using a new material to construct
a large warehouse in your city. This new material is cheaper than traditional building materials, but
it takes some time to learn how to use the material properly. You have communicated to the
project stakeholders that you will be able to save costs by using the new material, but you will
need a few extra weeks to complete training to use the materials. This risk response of learning
how to use the new materials can also be known as what term?