Which of the following risk processes is repeated after the plan risk responses to determine if the overall pr

You are the project manager of the NNN project for your company. You and the project team are
working together to plan the risk responses for the project. You feel that the team has successfully
completed the risk response planning and now you must initiate what risk process it is. Which of
the following risk processes is repeated after the plan risk responses to determine if the overall
project risk has been satisfactorily decreased?

which of the following risk prioritization options would this case be categorized?

You are the project manager of RFT project. You have identified a risk that the enterprise’s IT
system and application landscape is so complex that, within a few years, extending capacity will
become difficult and maintaining software will become very expensive. To overcome this risk the
response adopted is re-architecture of the existing system and purchase of new integrated
system. In which of the following risk

prioritization options would this case be categorized?

Where will you record the mitigation response?

You are the project manager for your company and a new change request has been approved for
your project. This change request, however, has introduced several new risks to the project. You
have communicated these risk events and the project stakeholders understand the possible
effects these risks could have on your project. You elect to create a mitigation response for the
identified risk events. Where will you record the mitigation response?


Page 511 of 751« First...102030...509510511512513...520530540...Last »