One or more solutions for each functional gap now have been identified where the solution
requires one to vary from using standard IBM Maximo Asset Management V7.1. Which two factors
are used to calculate the impact of each solution for the project success? (Choose two)

A.
Length
B.
Urgency
C.
Priority
D.
Risk to business
E.
Difficulty to implement