Which option should the integration developer select to resume and complete the failed activity?

An integration developer needs to analyze a failed activity in an instance in Business
Process Choreographer (BPC) Explorer. Exhibit 1 shows the process state for the failed
activity. Exhibit 1: The process stopped at CreditCheckService because the target service is
not available. Because it was not possible to determine the cause of failure at the time, the
integration developer decided to forcefully complete the failed activity by manually entering
the output data. The integration developer clicks the CreditCheckService activity to see the
menu option shown in Exhibit 2. Exhibit 2: Which option should the integration developer
select to resume and complete the failed activity? Jump to Another Activity to go to another
activity, click the next activity as a target activity:

PrepAway - Latest Free Exam Questions & Answers

A.
and choose Force Complete Source Activity and Jump. Enter the output data and click
Force Complete and Jump to complete the activity with the data provided.

B.
and choose Force Complete Source Activity and Jump. Enter the output data and click
Force Complete and Jump to complete the activity with the data provided.

C.
and choose Force Complete Source Activity and Jump. Enter the output data and click
Force Complete and Jump to complete the activity with the data provided.

D.
and choose Complete Source Activity and Jump. Enter the output data and click
Complete and Jump to complete the activity with the data provided.

E.
and choose Skip Source Activity and Jump.B.and choose Skip Source Activity and Jump.

F.
and cancel Jump.A.and cancel Jump.

G.
and choose Complete Source Activity and Jump. Enter the output data and click
Complete and Jump to complete the activity with the data provided.