Which of the following would account for this?

A developer has specified a maximum of two report processes for the application. While
monitoring the application, the developer notices that only one report process is running. Which of
the following would account for this?

PrepAway - Latest Free Exam Questions & Answers

A.
The number of affinity connections per BI Bus is set too high.

B.
The configuration size for the application is set too low.

C.
The number of low affinity connections has been exceeded.

D.
The number of report requests is too high.