What should be done to complete the Solution Project after collecting customer requirements and
educational/experience level of personnel, creating a solution design and proposal, and presenting
the solution proposal?

A.
have a formal IT Management sign-off on the purchase order
B.
schedule a formal service review with the chief operations officer and staff
C.
execute a formal review with the IT manager to confirm acceptance and solution compliance
D.
schedule a formal customer sign-off on the proposed Scope Document or Statement of Work
Explanation: