PrepAway - Latest Free Exam Questions & Answers

what is the penalty IBM imposes if a critsit arises in this circumstance?

IBM Business Partners face a penalty for Critical Situations (critsits) caused when a Technical Delivery

Assessment (TDA) is not followed.

In US dollars, what is the penalty IBM imposes if a critsit arises in this circumstance?

A. $1,000

B. $2,500

C. $10,000

D. $25,000

PrepAway - Latest Free Exam Questions & Answers

Answer: C

Explanation:
Explanation

Explanation/Reference: