How can the success of the scheduled backups be verified?

An IBM Tivoli Storage Manager V6.2 environment has scheduled backups which need to be checked to ensure that they are successful. How can the success of the scheduled backups be verified?

PrepAway - Latest Free Exam Questions & Answers

A.
run queryschedevents

B.
run querybackupevents

C.
run queryactlog sch=schedulename

D.
runcron using the reporting events module