Which of the following elements can be generated by material requirements planning (MRP)?

Which of the following elements can be generated by material requirements planning (MRP)? (Choose three.)

A. Production order

B. Purchase requisition

C. Planned order

D. Delivery schedule line

E. Purchase order

Reference: https://www.tutorialspoint.com/sap_pp/sap_pp_material_requirement_planning.htm