Who, as a minimum, should review the resourcing of a Programme Office whilst it is
running?

A.
Head of P3O and P3O Sponsor
B.
Head of Programme Office and Programme Manager of the relevant programme
C.
P3O Sponsor and Portfolio Analyst
D.
Head of COE and Programme Specialist