Which should be checked when a temporary Project Office is closing down?

Which should be checked when a temporary Project Office is closing down?

PrepAway - Latest Free Exam Questions & Answers

A.
Delivery of the P3O capability defined in the Blueprint is complete

B.
Continued alignment of P3O functions to the business requirements

C.
Transfer of the benefits management process to an operational area

D.
Realization of the benefits delivered by the P3O model