Which test management control option is most appropriate to adopt under these circumstances?

###BeginCaseStudy###
Scenario: 4
V2
Test Management Tool
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to
increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second
Increment slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver
the application with support for manual testing and then to provide a delivery * weeks later to
resolve any remaining points and provide support for automated testing (i.e. the link to the
capture-replay tool).
– Concerns have been expressed by a section of the user community, that in some places
the usability is very poor.
###EndCaseStudy###

Which test management control option is most appropriate to adopt under these
circumstances?

PrepAway - Latest Free Exam Questions & Answers

A.
Introduce mandatory evening and weekend working to retrieve the 3 week slippage.

B.
Reconsider the exit criteria and review the test plan in the context of the current situation.

C.
Advise the user community regarding the reduced scope of requirements and the
additional incremental delivery.

D.
Arrange a meeting with the user community representatives to discuss the user interface.