###EndCaseStudy### Identify THREE items that would be part of the work-breakdown structure showing the key te

###BeginCaseStudy###
Scenario: 7
Test Estimation
You have been contracted to manage the acceptance testing of a new computer-based
reservation system for a travel agency. You have provided an approximate budget estimate
for the testing project based on previous experience with similar sized projects. However, the
management of the parent company of the travel agency will not commit to the budget until
detailed cost estimates are provided. The reservation system is being developed by a third
party However, detailed specifications of the software are available, as well as an estimate
of the total effort that will be spent in developing the software. The software is to be delivered
in four increments, and the functionality to be delivered in each increment has already been
agreed on.
###EndCaseStudy###

Identify THREE items that would be part of the work-breakdown structure showing the key
testing activities for the acceptance test project.

PrepAway - Latest Free Exam Questions & Answers

A.
Test planning, test case preparation and test execution for each of the four iterations

B.
Work should be explicitly allocated to test completion, test management, installation and
to training on using the system

C.
Activities to deploy the system in the user environment

D.
Regression testing in the second, third and fourth iterations

E.
Development activities for unit and integration testing

F.
Reviews on requirements documentation

G.
Defining test environment requirements for system testing