Which statement about the Directing a Project process is FALSE?

A.
Supports the PRINCE2 principle of manage by exception
B.
Is triggered by a request to initiate a project
C.
Covers the day-to-day activities of the Project Manager
D.
Provides a mechanism for the Project Board to assure that there is continued business
justification
Explanation: