During the Managing a Stage Boundary process what product is updated with estimated costs and
time for the stage that is about to begin?

PrepAway - Latest Free Exam Questions & Answers

A.
End Stage Report

B.
Team Plan

C.
Work Package

D.
Project Plan

Explanation: