Which sequence of modes of engagement with a stakeholder would be followed as the level of their
interest in the programme increases?

A.
Keep informed, active consultation, maintain interest
B.
Keep informed, maintain interest, active consultation
C.
Active consultation, keep informed, maintain interest
D.
Maintain interest, active consultation, keep informed