Which is ensured by the Business Change Manager in the process Realizing the Benefits?

Which is ensured by the Business Change Manager in the process Realizing the Benefits?

PrepAway - Latest Free Exam Questions & Answers

A.
Optimal running of the programme verified by audits and reviews

B.
Effective benefits realization through creating a Benefits Management Strategy

C.
Readiness of the organization to implement the changes

D.
Alignment of project scope with benefits realization