which product is updated to incorporate the estimated time and costs from the Project Plan?

During the Initiating a Project process, which product is updated to incorporate the estimated time
and costs from the Project Plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Product Description

B.
Business Case

C.
Project Brief

D.
Project mandate