which product does a Project Manager define the time and cost tolerances for the work to be done by seenagape 10 years ago In which product does a Project Manager define the time and cost tolerances for the work to bedone by a Team Manager? A. Product Description B. Team Plan C. Work Package D. Stage Plan ← Previous question Next question →