which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Man

In which product does a Project Manager define the time and cost tolerances for the work to be
done by a Team Manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Product Description

B.
Team Plan

C.
Work Package

D.
Stage Plan