which process will the end users be informed that the reports have been damaged?

Two reports that have been produced in the nightly batch processing have been damaged during
printing. This has been noticed by Operational supplier management. In which process will the end
users be informed that the reports have been damaged?

PrepAway - Latest Free Exam Questions & Answers

A.
Business data management

B.
End user support

C.
Operational supplier management

Explanation: