Which of the following would be appropriate as a measure of test coverage?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

The business has asked for a weekly progress report. Which of the following would be
appropriate as a measure of test coverage?

PrepAway - Latest Free Exam Questions & Answers

A.
Percentage of business requirements exercised

B.
Percentage of planned hours worked this week

C.
Percentage of countries that have test scenarios

D.
Percentage of test iterations completed