Which of the following should be considered when designing measurement systems,
methods and metrics? 1. The services 2. The architectures 3. The configuration items 4.
The processes

A.
1, 3 and 4 only
B.
2, 3 and 4 only
C.
1, 2 and 3 only
D.
All of the above
When design measurement systems, methods and metrics, Services, Architectures, Configuration Items and processes should be considered