PrepAway - Latest Free Exam Questions & Answers

Which of the following is service transition planning and support NOT responsible for?

Which of the following is service transition planning and support NOT responsible for?

PrepAway - Latest Free Exam Questions & Answers

A.
Prioritizing conflicts for service transition resources

B.
Coordinating the efforts required to manage multiple simultaneous transitions

C.
Maintaining policies, standards and models for service transition activities and
processes

D.
Detailed planning of the build and test of individual changes

One Comment on “Which of the following is service transition planning and support NOT responsible for?

  1. jml says:

    Transition Planning and Support: The objectives of the transition planning and support process are to do the following:

    Plan and coordinate the resources for the transition
    Coordinate all of the various sources for the transitional activity.

    The scope of service transition planning and support covers the following:

    The maintenance of the policies and standards that are to be applied throughout the transition. This is important to ensure that the repeatable activity is managed appropriately and that you maximize the use of models for an efficient approach.

    Providing guidance for each new service or major change through the transition processes.

    Ensuring that the resources and management required for multiple transitions to take place at the same time are available.