Which of the following is NOT a typical key challenge for testing in a RAD based development approach?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Which of the following is NOT a typical key challenge for testing in a RAD based
development approach?

PrepAway - Latest Free Exam Questions & Answers

A.
Re-usable test scripts for (automated) regression testing

B.
Project management and control

C.
No complete requirements specification

D.
Time-boxing