PrepAway - Latest Free Exam Questions & Answers

Which of the following availability management activities is/are considered to be proactive as opposed to reac

Which of the following availability management activities is/are considered to be proactive
as opposed to reactive? 1. Monitoring system availability 2. Designing availability into a
proposed solution

PrepAway - Latest Free Exam Questions & Answers

A.
None of the above

B.
Both of the above

C.
1 only

D.
2 only


Leave a Reply