Which is NOT a requirement of a Stage Plan?

A.
Produced to an appropriate level of detail to enable day-to-day control
B.
Produced near to the end of the previous management stage
C.
Approved and signed-off by Project Assurance
D.
Approved at the end of a management stage
Explanation: