Which is a purpose of measuring Key Performance Indicators for a P3O?

A.
Demonstrate a P3O’s successes to the organization
B.
Determine project progress against its plan
C.
Identify the resources required within a P3O
D.
Identify areas of personal improvement for Project Managers