Which is a purpose of a Risk Register?
A.
Capture risks that may occur during the project
B.
Record how risk management activities will be undertaken on the project
C.
Record the risk tolerance for the project
D.
Capture issues which are impacting on the delivery of the project objectives
Explanation:
