Which is NOT a typical Key Performance Indicator which can be used to measure the
success of a P3O?

A.
Increased success of programmes delivering to budget
B.
Improved portfolio balance in relation to spend on short term contract resource
C.
Increased use of implemented tools by operations staff
D.
Enhanced contribution measured against the Benefits Realization Plan