Which activity takes place within the Managing a Stage Boundary process?

A.
Produce Highlight Reports
B.
Take corrective action within the limits of a stage’s tolerance
C.
Produce an Exception Plan
D.
Authorize a Stage Plan for the next stage
Explanation: