What is bottom-up scheduling?

What is bottom-up scheduling?

PrepAway - Latest Free Exam Questions & Answers

A.
Team members representing each role generate time estimates and schedules for deliverables.
Each team schedule is integrated intoaTeam members representing each role generate time
estimates and schedules for deliverables. Each team? schedule is integrated into a
master project schedule.

B.
The program manager estimates the time required for each team member to complete his or
her tasks, and then validates those estimates with
the team members.

C.
The program manager builds a master project schedule based on industry standards for each
task.

D.
The solution manager estimates the time required for each team member to complete his or her
tasks, and then validates those estimates with
the team members.