What is an information radiator?
What is an information radiator?
What is the most likely reason that the team did not meet the Sprint objectives?
A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and
was away for two days right at the beginning of the four week Sprint.
What is the most likely reason that the team did not meet the Sprint objectives?
What would be the elapsed time required to complete the Story?
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets
about four hours of actual work time.
What would be the elapsed time required to complete the Story?
Who knows most about the progress towards a business objective or a release?
Who knows most about the progress towards a business objective or a release?
What is the best way to split up teams on a large project which is implemented using Scrum?
What is the best way to split up teams on a large project which is implemented using Scrum?
What term best describes this type of interaction?
Collaboration is the most important parameter for the success of an Agile team.
What term best describes this type of interaction?
What is the elapsed time required to complete the story?
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about
six hours of work done on a daily basis.
What is the elapsed time required to complete the story?
Where should a Scrum Master be located?
A team has eleven members spread over two locations across two time zones. One of the
locations has six team members and the other team has five.
Where should a Scrum Master be located?
What makes the bar become longer?
For a Sprint, progress is monitored in a burn-up chart with bars.
What makes the bar become longer?
what would your best advice be?
A 200 member project team is working on a large and complex system with multiple sub-systems.
They would like to start using the Agile Scrum methodology.
As a Scrum Master, what would your best advice be?