what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
Under what circumstances would a team use Affinity Estimation Technique instead of Planning
Poker?
What is the objective of the Scrum-of-Scrums meeting?
What is the objective of the Scrum-of-Scrums meeting?
What is the velocity of the team?
During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They
further complete half a story with a story point of 13.
What is the velocity of the team?
Which statement describes Release Planning?
Which statement describes Release Planning?
What term best describes the multi-level planning?
Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan.
What term best describes the multi-level planning?
How does Agile bring predictability to the Planning process?
How does Agile bring predictability to the Planning process?
What should be done to set the priorities?
During the release planning meeting, it is difficult to agree on priorities.
Sales want to implement some new features to catch up with the competitors.
Marketing want to work on a mobile interface that can prove to be a competitive differentiator.
Customer support want better logging and auditing capabilities to improve maintainability.
What should be done to set the priorities?
How should ‘done’ be defined when multiple teams are working on a single product?
How should ‘done’ be defined when multiple teams are working on a single product?
What is the best course of action for the team?
Near the end of a Sprint, the team realizes that they will not be able to complete the stories they
had committed to.
What is the best course of action for the team?
What is an "escaped defect"?
What is an “escaped defect”?